We Interchange With

LRWY has received a $3653,500 grant with a required $151,500 in matching funds ($505,00 total) from Pennsylvania Department of Transportation (PennDOT) Bureau of Rail Freight, Ports, and Waterways (BRFPW), Rail Freight Assistance Program (RFAP) for upgrades to Wyalusing Station.  Two seperate contracts will be let, one for track work and one for paving.

Contract 1 is for replacement of one (1) #10 and one (1) #8 turnout and raising of about 1000' of industrial spur track.

Contract 2 is for grading and paving of the 110,000 sq. ft. transload area.

May 13, 2015 - Bid packages advertised in 3 local newspapers.

May 29, 2015 - Bids opened.  Five (5) bids received for track work and two (2) bids received for paving.  All bids were rejected because the bid price was significantly over available budget and and an insufficient number of bidders responded to the paving work.

July 08, 2015 - New bid packages advertised.  Track work reduced in scope to raising of one (1) industrial spur.  Paving reduced in scope by reducing area to be paved, using more asphalt vice concrete, and reducing the volume of fill.

July 24, 2015 - Bid opening. Five (5) bids received.  Three (3) for paving, two (2) for trackwork.  LRWY will be recommending that PennDOT accept the bids from Railworks and M.R. Dirt.

Track Work Bids                                                                                                          
BIDDER  BID AMOUNT  
 W.J. Riegel         $82,444.00                                                                                  
  Railworks $72, 220.00  

 

Paving Bids                                                                                                          
BIDDER BID AMOUNT                                                                                    
 Bishop Brothers  $568,082.25   
 M.R. Dirt $475,690.00   
 G. O. Hawbaker $508,263.00  

 

Augsut 7, 2015 - Notice of award sent and accepted by both contractors.

August 10, 2015 - Executed contract with M.R. Dirt, Inc and RailWorks Track Serices, Inc.

August 31, 201 5 - Track work kick-off meeting with RailWorks Track Services, Inc.

September 01, 2015 - Pre-construction meeting with M.R. Dirt Inc.

September 14, 2015 - Start of work.

September 25, 2015 - Certificate of significant completion issued.

October 08, 2015 - PennDOT inspection. No defects found.

Please direct all inquiries to Tom Clark, (607) 687-6786.